Easter opening event planned for Melton's new bypass

An opening event for Melton Mowbray’s new partial bypass is being planned for Easter with all of the major construction elements now completed.

Leicestershire County Council has not established an exact date for when the North East Melton Mowbray Distributor Road (NEMMDR) will be open to traffic – a spokeswoman for County Hall told the Melton Times that ‘opening is still expected in late spring’.

The new MMDR where it intersects with roundabout 5 on the B676 Saxby Roadplaceholder image
The new MMDR where it intersects with roundabout 5 on the B676 Saxby Road

And a report to go before next week’s highways, transport and waste overview and scrutiny meeting states that detailed arrangements are still be finalised for the opening event ‘which is expected to take place around Easter’.

The new road will connect the A606 Nottingham Road to the north of the town with the A606 Burton Road to the south – the 7.1km single carriageway will pass to the east of Melton passing through six new roundabouts.

The railway bridge on the MMDR - one of the biggest construction challenges on the routeplaceholder image
The railway bridge on the MMDR - one of the biggest construction challenges on the route

The project represents the largest capital highways scheme that has ever been undertaken by Leicestershire County Council, with preliminary work beginning back in 2015 and work finally starting in May last year.

The cost of the road has soared to £134M from the initial estimate of £63.5M due mainly to rising construction costs and inflationary pressures.

Residents in the Melton borough will get a chance to select the name from a shortlist of suggested names – the borough council is co-ordinating this and will soon launch a public poll to choose.

There will also be opportunities for local businesses to get sponsorship hoardings on each of the roundabouts along the route.

Engineers have overcome significant challenges to build the road, including putting in four bridges, installing numerous culverts and diverting the path of the River Eye to protect natural habitats.

Cycling and walking paths are being built alongside the highway to create new exercise resources for locals.

The report to go before county councillors states: “The work is now at the advanced stage, with the majority of structures completed including bridges at the railway, River Eye, Scalford Brook and Thorpe Brook.

"All six new roundabouts have now been completed, and they are open to traffic.

“The River Eye Site of Special Scientific Interest (SSSI) relocation went extremely well, and we have received positive feedback from Natural England.

"The new river channel and flood compensation areas performed well in recent storms

“The new railway bridge similarly was a large piece of engineering and has been completed with positive feedback from Network Rail.”

Several major challenges have increased the cost of the scheme and extended the time of construction, including Storm Babet in October 2023, which was the wettest three-day period ever recorded in the midlands.

There was also flooding during the building of the new bridge of the River Eye.

Piling work on the site was carried out using the largest piling rig in Europe.

Archaeologists have also carried out digs across around 25 hectares along the route – evidence of a large Roman farmstead was unearthed early in the project.

The cost of the road has been met mainly through £49M government money, housing developer contributions and forward funding from the county council.

The report adds: “Significant budgetary pressures (such as flooding, utilities, archaeology) have contributed to increased costs. The current forecast cost is £134.6M.”